The project, which was completed, was conducted to make the road on the same level by removing the debris and preparing the street after the removal of the obstacles.
Then, the working staff covered the street with sand in a thickness of 60 cm along the street of 500 m and with a width 7 m, then covering it with 15 cm of gravel with appropriate preparation and suitable water spraying.