The works were divided according to the plan developed by the implementing company; Ard Al-Qods company for Constructions under the direct and field supervision of the projects' department at the Al-Abbas's (p) Holy Shrine, which director has explained to Al-Kafeel Network: "This project was divided into three parts, the first was in the western side opposite to the gates of Imam Al-Hussayn and of Saheb Zaman (peace be upon both of them). The second is in the southern side in the opposite of the gate of Imam Al-Jawad (peace be upon him) and the third is on the eastern side in the opposite of the gate of the Euphrates ('Alqami)."
Continuing: "The project has passed through several stages until arriving at its final form. The stages were as follows:
First: Uprooting the old Kashi Karbalai and removing the stucco waste and the old linking materials down to the original.
Second: Maintenance of these walls by treating its cracks using modern techniques and specific material for this purpose.
Third: Strengthening the original walls with a supporting concrete wall and an entire iron structure, using a thickness that was identified according to the need and in proportion to the dimensions of each wall.
Fourth: Fixing wires for the electricity, lighting and sound systems to connect it with the holy shrine's system.
Fifth: Fixing the pieces of the metal clamp that is away from the wall to install the tiles on it.
Sixth: Installing the streaky Kashi Karbalai, which is the same type used in all the corridors of the holy sanctuary to ensure the creation of a state of artistic and engineering symmetry.
Mr. Al-Sa'egh has also stated: "With the end of this project, we have finished an important stage to be added to other stages and works carried out in the holy sanctuary of Aba Al-Fadl Al-Abbas (peace be upon him), by taking into account in its implementation and finishing, the creation of a geometry symmetry with the rest of the parts of the holy shrine.”